UL AND SEYSES ARE WORKING ON THE OPERATION AND MAINTENANCE OF THE VILLA AHUMADA PHOTOVOLTAIC PARK

Since last March, UL and SEYSES have been collaborating in the Operation and Maintenance activities at the Villa Ahumada solar park.

seyses-ul-parque-fotovoltaico-villa-ahumada

The construction and commissioning of the 150 MW solar panel park is located on approximately 500 hectares of land adjacent to the Moctezuma substation, next to highway 45 Chihuahua-Juárez, in the state of Chihuahua, Mexico.

seyses-mexico-villa-ahumada-ul

After several collaborations, UL has trusted, once again, in SEYSES Project Management services for the incorporation of the expert team in electrical and mechanical tests, in charge of carrying out the necessary works for the correct operation of the plant.

Recent Posts